Steady progress is being made at Masi Educare pre-school. We last reported on the preparatory work for the delivery of new classrooms back in May. It is pleasing to see how much has been achieved in the months since then as shown by the photographs below.
As can be seen in the pictures above the walkways between the new classrooms and the main building are about two-thirds complete. Nearly all roof trusses are in place, with roof panels to be delivered by the end of this week.
Everything remains in place for the main construction to be completed by the end of October, with internal work continuing until the end of the year. Our thanks to the team on site led by Masicorp volunteer Colin Blaikie.